Reply #4: All economic reports are very clear - merchant nuclear cannot proceed ... [View All]

Printer-friendly format Printer-friendly format
Printer-friendly format Email this thread to a friend
Printer-friendly format Bookmark this thread
This topic is archived.
Home » Discuss » Topic Forums » Environment/Energy Donate to DU
kristopher Donating Member (1000+ posts) Send PM | Profile | Ignore Wed May-26-10 12:52 PM
Response to Original message
4. All economic reports are very clear - merchant nuclear cannot proceed ...
...unless ALL risks are shifted to the public sector.

Citigroup Nov 2009 analysis

New Nuclear – The Economics Say No

UK Green Lights New Nuclear – Or Does It?


 Green lighting new nuclear? — The UK government today announced a fast-track planning process for new nuclear power stations. 10 sites have been approved for possible development. The government is presenting today’s announcement as providing the green light for a major new nuclear programme, which it says is needed to meet climate change and security of supply targets.

 But no financial support has been offered — The government has not announced any direct financial support for new nuclear. The government still seems to expect the private sector to take an unacceptable level of risk, in our view.

 The five big risks — Nuclear power station developers face five big risks:
Planning,
Construction,
Power Price,
Operational, and
Decommissioning.

The government today has sought to limit the Planning risk. While important for encouraging developers to bring forward projects, this is the least important risk financially.

 The three Corporate Killers — Three of the risks faced by developers — Construction, Power Price, and Operational — are so large and variable that individually they could each bring even the largest utility company to its knees financially. This makes new nuclear a unique investment proposition for utility companies.

 No where else in the world — Government policy remains that the private sector takes full exposure to the three main risks; Construction, Power Price and Operational. Nowhere in the world have nuclear power stations been built on this basis.

 Nor will they be built in the UK — We see little if any prospect that new nuclear stations will be built in the UK by the private sector unless developers can lay off substantial elements of the three major risks. Financing guarantees, minimum power prices, and / or government-backed power off-take agreements may all be needed if stations are to be built.





Printer Friendly | Permalink |  | Top
 

Home » Discuss » Topic Forums » Environment/Energy Donate to DU

Powered by DCForum+ Version 1.1 Copyright 1997-2002 DCScripts.com
Software has been extensively modified by the DU administrators


Important Notices: By participating on this discussion board, visitors agree to abide by the rules outlined on our Rules page. Messages posted on the Democratic Underground Discussion Forums are the opinions of the individuals who post them, and do not necessarily represent the opinions of Democratic Underground, LLC.

Home  |  Discussion Forums  |  Journals |  Store  |  Donate

About DU  |  Contact Us  |  Privacy Policy

Got a message for Democratic Underground? Click here to send us a message.

© 2001 - 2011 Democratic Underground, LLC