One of the UK's largest wind farm developers has threatened to pull out of the country as a storm blows up over the Government's plans for renewable energy.
A logjam in the planning process for developers means that many wind farms will not be operational for a decade. Unless financing rules are changed, Wind Energy is warning that many will never even get built, which could force the Government to miss its targets on renewable energy. The timing of the protest is embarrassing for the Government, which next month will close consultation on its energy review on nuclear power. Its previous review - only three years ago - was supposed to back renewable energy such as wind power.
Wind Energy wants to build 800MW of onshore wind farms in Scotland, enough to power a city the size of Edinburgh. National Grid has told the company, and developers of around 100 other wind farms in Scotland, totalling around 6,000MW, that they will not be connected to the grid before 2016.
But despite the huge timelag, developers still have to table deposits upfront to cover the cost of the upgrades to the grid - even if planning permission for their site is not granted and the wind farm does not go ahead.
EDIT
http://news.independent.co.uk/business/news/article352112.ece