West Seattle Bridge opening delayed another two months
West Seattle residents are going to have to wait until September before the high bridge reopens.
The scheduled early summer reopening has been pushed back more than two months because of the King County concrete strike earlier this year. The contractor had planned to pour the concrete for the steel support beams inside the bridge at the start of the year. Seattle Mayor Bruce Harrell set a February 20 deadline for the strike to end before the reopening would be impacted. The concrete didnt arrive until mid-April.
There had been hope that the contractor could make up the time and keep the schedule somewhat intact, but that didnt happen. The two-month delay in getting the concrete after that deadline turned into a two-month delay in the reopening.
Work on the bridge was scheduled to end in June, and then open to traffic after a few days of load testing to make sure the bridge was ready for cars.