Vogtle project cost drops, Ga. Power says
Georgia Power Co. executives told the Public Service Commission Wednesday that the cost of financing two new reactors at Plant Vogtle is dropping another $1 billion, but the first electricity from them will come eight months later than planned. Their comments came in testimony during the commissions semi-annual cost review. While construction costs have only fluctuated about $28 million from the original estimate, the financing expense is now nearly $2 billion lower because of several factors.
Kyle Leach, the director of resource planning for the giant utility, credits lower interest rates in bond sales last week and in March with the latest savings to power customers. Earlier, the company announced the initial savings figure attributed to federal loan guarantees, inflation-protection agreements and a controversial law that has customers paying some of the finance charges up front.
Georgia Power has been selling its bonds to investors 3-4 percentage points lower than what it expected five years ago when the commission originally approved the project. By the end of the year, most of the financing will be in place, but Leach acknowledged that a spike in interest rates next year could erase some of those savings.
At the same time, the cost of building the reactors could go up. That depends on negotiations between Georgia Power and its construction company over whos to blame for $400 million in changes to the blueprints, including installation of steel-reinforcement rebar in the concrete different from what was specified. Those negotiations have been more protracted than we anticipated, Leach said.
http://chronicle.augusta.com/latest-news/2012-05-09/vogtle-project-cost-drops-ga-power-says?v=1336586301