Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News Editorials & Other Articles General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

Science

Showing Original Post only (View all)

TexasTowelie

(127,436 posts)
Thu Oct 11, 2018, 07:25 AM Oct 2018

NASA's Mars rocket is behind schedule and over budget due to 'Boeing's poor performance,' audit find [View all]

Years of delays and billions of dollars of cost overruns have marred Boeing’s building of key components of a next-generation rocket that one day is meant to take humans to the moon and Mars, according to a scathing audit released Wednesday by NASA’s Office of the Inspector General.

The report also found that in addition to Boeing’s mistakes, NASA was being overly generous with its evaluations of the company, leading to questionable payments.

Under a NASA contract, Boeing is currently building two core stages for the Space Launch System, a heavy-lift rocket that will carry the Orion spacecraft and astronauts into deep space. Boeing’s contract is the largest in the Space Launch System program, comprising more than 40 percent of the program expenditures

Boeing’s parts will be integrated with other components of the rocket at Kennedy Space Center, before they launch from the Space Coast.

Read more: https://www.orlandosentinel.com/news/space/go-for-launch/os-nasa-sls-delay-report-20181010-story.html

2 replies = new reply since forum marked as read
Highlight: NoneDon't highlight anything 5 newestHighlight 5 most recent replies
Latest Discussions»Culture Forums»Science»NASA's Mars rocket is beh...»Reply #0